After a PR is submitted, a core committer applies labels and notifies product managers (PMs) that there is a PR awaiting review by posting in the [PM/Docs PR Review channel](https://pre-release.mattermost.com/core/channels/pmdocs-pr-review-pub), which is a channel to discuss community pull requests that need review by PMs. After a PR is submitted, a core committer applies labels and notifies product managers (PMs) that there is a PR awaiting review by posting in the [PM/Docs PR Review channel](https://pre-release.mattermost.com/core/channels/pmdocs-pr-review-pub), which is a channel to discuss community pull requests that need review by PMs.
Then, one or more of the labels is applied: Then, one or more of the labels is applied:
- `Awaiting PR`: Applied if the PR is awaiting another to be merged. For example, when a client PR is awaiting a server PR to be merged first. Once the PR is no longer blocked, the core committer removes the `Awaiting PR` label - `Awaiting PR`: Applied if the PR is awaiting another to be merged. For example, when a client PR is awaiting a server PR to be merged first. Once the PR is no longer blocked, the core committer removes the `Awaiting PR` label.
- `1: PM Review`: Applied if the PR has UI changes or functionality that PMs can test on test servers called "spinmints" - `1: PM Review`: Applied if the PR has UI changes or functionality that PMs can test on test servers called "spinmints".
- `Major Change`: Applied if the PR is a major feature or affects large areas of the code base, e.g. [moving channel store and actions to Redux](https://github.com/mattermost/platform/pull/6235) - `Major Change`: Applied if the PR is a major feature or affects large areas of the code base, e.g. [moving channel store and actions to Redux](https://github.com/mattermost/platform/pull/6235).
- `Setup Test Server`: Applied if the PR is queued for PM testing - `Setup Test Server`: Applied if the PR is queued for PM testing.
- `Work in Progress`: Applied if the PR is unfinished and needs further work before it's ready for review - `Work in Progress`: Applied if the PR is unfinished and needs further work before it's ready for review.
#### Stage 1: PM Review #### Stage 1: PM Review
A product manager will review the pull request to make sure it: A product manager (PM) will review the pull request to make sure it:
- Fits with our product roadmap.
- Works as described in the ticket.
- Meets [user experience guidelines](https://docs.mattermost.com/developer/fx-guidelines.html).
- Fits with our product roadmap This step is sometimes skipped for bugs or small improvements with a well-defined ticket. In this case the core committer will assign the appropriate devs for review. A PM can also ask developer support to set up a separate test instance if the PR cannot be easily tested.
- Works as described in the ticket
- Meets [user experience guidelines](https://docs.mattermost.com/developer/fx-guidelines.html)
This step is sometimes skipped for bugs or small improvements with a well defined ticket. When the review process begins:
- Mattermost Core Committer
- Assigns `1: PM Review` label within 1 business day after the PR is submitted.
- Assigns PM reviewer under Assignees. Those related to end user features are assigned to @esethna, others to @jasonblais. PM re-assigns as needed.
- PM
- Applies milestone for next release if the PM thinks there is enough time for the PR to be merged and sufficiently tested on `master` before code complete. Otherwise moved to a future release, letting submitter know that PR may have a delay in review due to the release cycle.
- Follows up with contributor if the CLA has not been signed. If no response within 7 days, PM closes the issue.
- PM verifies there is a corresponding JIRA ticket or GitHub issue.
When the review process begins, the PM applies a milestone: Next, the PM tests changes on a spinmint test server:
- Set for next release if the PM thinks there is enough time for the PR to be merged and sufficiently tested on `master` before code complete. - PM tests and verifies pull requests via the `Setup Test Server` label. Initial review is completed within 2 business days.
- Set for a future release if PR is too large to test prior to the code complete date
- PM responds to submitter letting them know that PR may have a delay in review due to the release cycle
Next, the PM tests changes on the spinmint:
- If changes are required, PM submits review as "Changes Requested", with a comment on the areas that require updates. Comment explains why changes are needed linking back to design principles. - If changes are required, PM submits review as "Changes Requested", with a comment on the areas that require updates. Comment explains why changes are needed linking back to design principles.
- PM applies `Awaiting Submitter Action` label to more easily query the PR queue - PM applies `Awaiting Submitter Action` label to more easily query the PR queue.
- Once changes are made, PM regenerates test server and repeats testing. - Once changes are made, PM regenerates test server and repeats testing.
- If bugs are found that are also on `master`, a new bug report is submitted in JIRA and linked to the PR. Bugs that are also found on `master` will typically not block merging of PRs. - If bugs are found that are also on `master`, a new bug report is submitted in JIRA and linked to the PR. Bugs that are also found on `master` will typically not block merging of PRs.
- If PR is approved, PM submits review as "Approved" commenting with areas that were tested. Then: - If PR is approved, PM submits review as "Approved", commenting with areas that were tested.
- PM removes `1: PM Review` and `Setup Test Server` labels
- PM applies the `Stage 2: Dev Review` label, which moves the PR to Stage 2
#### Stage 2: Dev Review #### Stage 2: Dev Review
Two developers will review the pull request and either give feedback or approve the PR. If changes are required: Two developers will review the pull request and either give feedback or approve the PR. Any comments should be addressed before the pull request moves on to the next stage.
- Dev submits review as "Changes Requested", with a comment on the areas that require tweaks.
- Once changes are made, dev reviews code changes
Any comments should be addressed before the pull request moves on to the last stage. - PM reviewer adds `2: Dev Review` label, removes `1: PM Review` and `Setup Test Server` labels, and assigns 2 developers for review under Reviewers.
- At least one dev is assigned based on their [feature area](https://docs.mattermost.com/developer/core-developer-handbook.html#current-core-developers). Devs re-assign as needed.
- Devs review the code and provide feedback, with initial review completed within 2 business days. Some areas to check include:
- Proper Unit Tests
- API documentation
- Localization
- After the submitter has addressed and satisfied all reviewers' comments, `3: Ready to Merge` label is applied.
#### Stage 3: Ready to Merge #### Stage 3: Ready to Merge
The review process is complete, and the pull request will be merged. Review process is complete and the pull request is merged.
- Dev assigns `3: Ready to Merge` label.
- If Mattermost is not in release mode (between [major feature cut and release candidate cut](https://docs.mattermost.com/process/release-process.html), the PR is merged into `master`.
- If the PR is a major change, merge is postponed until the next release cycle.
- Dev calls out on the issue that it is a major change and it will be merged after branching.
- Once the current release is branched the PR can be merged into `master`.
#### PR Merged #### PR Merged
After a PR is merged: After a PR is merged:
- External Contributions: PM closes the [Help Wanted] issue and related Jira ticket - External Contributions: PM closes the [Help Wanted] issue and related JIRA ticket.
- Internal Contributions: Core committer resolves the JIRA ticket - Internal Contributions: Core committer resolves the JIRA ticket.
- PM follows up for docs, changelog and release tests when working through the PR tracking spreadsheet - PM follows up for docs and changelog, and QA for release tests.